Williams Micropile Systems Support Hurricane Helene Recovery in Tennessee
Location: Hartford, Tennessee
Project: I-40 TDOT Slide Repair
Contractor:
Project Start: November 2025 – Ongoing
Application: Permanent Structure Micropiles
Williams Product: #18 Epoxy-Coated Grade 80 Bar
Project Overview
Following the significant damage caused by Hurricane Helene, restoration and stabilization work along Interstate 40 near Hartford, Tennessee required a long-term solution designed to help protect critical infrastructure in the affected river basin.
The I-40 TDOT Slide Repair project is part of the broader Hurricane Helene recovery and restabilization effort. Multiple contractors are working concurrently in the area to repair and reinforce infrastructure affected by the storm. A key element of the project involves constructing a permanent concrete structure near the river basin to provide greater stability and help mitigate the potential for similar damage in the future.
The Application
Permanent micropiles are being incorporated into the stabilization structure to provide deep foundation support. The project requires a solution capable of supporting a long-duration, high-volume construction schedule while meeting the demands of a permanent infrastructure application.
Williams Form Engineering is supplying #18 epoxy-coated Grade 80 bar for the micropile system.
Why Williams?
For a project of this duration and scale, product availability, competitive pricing and dependable supply are critical. Williams was selected based on a combination of pricing, schedule requirements and the long-standing relationship between the companies.
The project’s extended schedule and high material volume make consistency and coordination especially important. Williams’ established relationship with the project team provides a reliable supply partner throughout the ongoing construction effort.
What Makes the Project Unique
This is more than a conventional infrastructure improvement project. The work is directly connected to Hurricane Helene relief and long-term restabilization, with multiple contractors operating simultaneously around the same structures.
The permanent concrete structure being constructed near the river basin is intended to strengthen the area and reduce its vulnerability to the type of damage experienced during Hurricane Helene.
Williams Products Used
#18 Epoxy-Coated Grade 80 Bar
Application: Permanent Structure Micropiles
Williams’ high-strength threaded bar systems are well suited to demanding foundation and earth-retention applications where dependable load transfer, installation efficiency and long-term performance are required.
Building Back with Long-Term Resilience
The I-40 TDOT Slide Repair demonstrates the role that engineered foundation systems can play in rebuilding critical infrastructure following a major natural disaster. By supporting the permanent micropile portion of the project, Williams Form Engineering is contributing to a long-term stabilization solution designed to help protect this important transportation corridor and the surrounding infrastructure.
Special thanks to our friends at Goettle.