Spin-Lock Rock Anchor Installation

Spin-Lock
Information
Parts &
Accessories
Head
Assemblies
Spin-Lock Installation
Installation
Equipment
Case
Histories
Corrosion
Protection
Step #1 Drilling
Use Standard Rotary Percussion Equipment
Step #1 Drilling Drawing

Step #1 Drilling Photo

Care should be taken to insure an accurate diameter and a straight hole. The depth should be over drilled to allow any debris to fall to the bottom of the hole when the anchor is inserted. Clean the drill hole by blowing air to the full depth to remove debris. Efforts should be made to prepare the collar area with a flat surface and as perpendicular to the bolt axis as possible.
Step #2 Bolt Placement
Step #2 Bolt Placement Drawing

Step #2 Bolt Placement Photo

Place the nut, washer, bevel washers (if required), and plate on the rock bolt and push the bolt into the hole to the correct embedment depth. If the bolt becomes stuck in the hole, attach a setting tool to the end of the bolt and drive it into the hole with a sledgehammer.
Step #3 Setting the Anchor
Step #3 Setting the Anchor Drawing

Step #3 Setting the Anchor Photo

Install setting tool fully onto the exposed threaded end. Provide space between the setting tool and the hex nut. Initially torque the bolt to the required torque with an impact gun, pneumatic, or hydraulic torque wrench. This action migrates the cone into the shell, thus expanding the mechanical anchor into the rock. Final torque can be checked and adjusted with a manual or hydraulic torque wrench. Remove the setting tool by restraining the lower part while rotating it's upper section until the setting tool is loose. Prepare collar area with fast setting grout to ensure full bearing under the plate.
Step #4A Testing the Anchor Bolt
Method A - Tensioning with a Test Jack
Step #4A Testing the Anchor Bolt Drawing

Step #4A Testing the Anchor Bolt Photo

Place the jack and frame over the bolt and attach the test rod and couplings to the bolt. Attach the test nut and test plate over the test rod on top of the jack. Test the rock bolt by tensioning the jack to the required test load (usually half of the ultimate strength) but never to exceed the advertised yield strength of the anchor. Adjust the loading of the jack to the required final tension and lock in the final pre-stress load. This is done by tightening the rock bolt hex nut with a knocker wrench (through the frame opening) until a slight reduction is noticed on the jack gauge. The full pre-stress load will be transferred to the anchor bolt once the tension in the test jack has been released and test components removed.
Step #4B Testing the Anchor Bolt
Method B - Testing by Tourque Tensioning
Step #4B Testing the Anchor Bolt Drawing

Step #4B Testing the Anchor Bolt Photo

Place plate, bevel washers (if required), hardened washer, and hex nut on the rock bolt. Tension the bolt by torquing the hex nut with a torque wrench. For the recommended torque valve to obtain the advertised tensile working load, see the "Torque On Nut" column on the Spin-Lock Bolt charts. For other loads, see the torque tension graphs. Please Note: The torque/tension relationship is not as accurate as direct tensioning with a hydraulic jack and should not be used where critical tension loads need to be verified.
Step 5: Grouting the Anchor
Step #5 Down Grouting Drawing

Down Grouting

Step #5 Down Grouting  Photo

Always grout from the lowest gravitation point on the anchor bolt until a steady stream of pure grout is seen coming out around the bearing plate or grout tube, and/or from the de-air tube. For solid bolts, this means that a separate grout tube must be placed in the drill hole (through an opening in the bearing plate) as deep as possible before grouting. Long length solid bolts should have the grout tube attached to the bolt before inserting and setting the anchor. Down-grouting of Hollow Core Rock Bolts can be simply grouted through the hollow core by attaching a grout tube adapter to the outer end of the tensioned bolt and grouting. When the grouting is complete, all air and standing water has been removed from the drill hole by displacement and all cracks and voids in the anchor area are filled with cement grout.
Step #5 Up Grouting Drawing

Up Grouting

Step #5 Up Grouting  Photo

Up-grouting of Hollow-Core Rock Bolts can be done by grouting through a short length grout tube extending just past the drill hole sealer in the collar area thus using the hollow core at the end of the rock bolt to de-air the hole. Up-grouting of solid rock bolts involves attaching a long length grout tube to the anchor (prior to insertion, setting, and tensioning) and grouting through a separate short length tube that extends past the sealer area thus allowing the rock bolt to de-air from the longer grout tube.
Final Thoughts
Williams offers a field installation advising service to aid contractors in the initial installation process of installing all types of anchor bolts. A Williams "Spin-Lock Anchor Installation Video" is also available here. Contact your Williams sales representative for details.
Williams Form Engineering Corp.
Spin-Lock
Information
Parts &
Accessories
Head
Assemblies
Spin-Lock Installation Installation
Equipment
Corrosion
Protection
Case
Histories
Contact Us Home
Williams Form Engineering Corp. All rights reserved.